19 December 2024 ROTAX issued MANDATORY ROTAX Service Bulletin Inspection and/or replacement of expansion tank assy. for
ROTAX® 912, 914, 912 i, 915 i and 916 i
Below the engines installed in ARGONS Gyroplanes affected this bulletins:
10001685 - ROTAX 916 iS
10001769 - ROTAX 916 iS
10002588 - ROTAX 916 iS
10002589 - ROTAX 916 iS
10003674 - ROTAX 916 iS
10002921 - ROTAX 915 iS
Reason:
Due to a deviation in the manufacturing process, the individual components of the expansion tank assy. may not be sufficiently welded. Sealing of the assy. may be compromised and coolant leakage and subsequently an overheating of the engine may occur.
Subject:
Inspection and/or replacement of expansion tank assy. for ROTAX® 912, 914, 912 i, 915 i and 916 I (Series) Aircraft Engines.
Compliance:
- Uninstalled engines/spare parts prior to usage but no later than 31 December 2025.
- If coolant leakage is detected at the required pre-flight check, immediate action should be taken.
- At next scheduled maintenance event or at least within the next 25 hours of operation, carry out this inspection and/or replacement must be conducted according to the following instructions in section 3, but at the latest after 1 year (from the date of the initial issue of this Service Bulletin).
ROTAX® 912, 914, 912 i, 915 i and 916 i
Below the engines installed in ARGONS Gyroplanes affected this bulletins:
10001685 - ROTAX 916 iS
10001769 - ROTAX 916 iS
10002588 - ROTAX 916 iS
10002589 - ROTAX 916 iS
10003674 - ROTAX 916 iS
10002921 - ROTAX 915 iS
Reason:
Due to a deviation in the manufacturing process, the individual components of the expansion tank assy. may not be sufficiently welded. Sealing of the assy. may be compromised and coolant leakage and subsequently an overheating of the engine may occur.
Subject:
Inspection and/or replacement of expansion tank assy. for ROTAX® 912, 914, 912 i, 915 i and 916 I (Series) Aircraft Engines.
Compliance:
- Uninstalled engines/spare parts prior to usage but no later than 31 December 2025.
- If coolant leakage is detected at the required pre-flight check, immediate action should be taken.
- At next scheduled maintenance event or at least within the next 25 hours of operation, carry out this inspection and/or replacement must be conducted according to the following instructions in section 3, but at the latest after 1 year (from the date of the initial issue of this Service Bulletin).